Name
Start
End
Milestone
Progress
Assign To
Edit Notes...
Onset DocumentationJul 1, 2005Aug 27, 2005 18
 
Project CharterJul 1, 2005Aug 25, 2005 51
 
project charter first draftJul 1, 2005Jul 29, 2005 100George Kerscher
 
project charter review and finalizationJul 29, 2005Aug 25, 2005 0Markus Gylling, Marisa DeMeglio, George Kerscher
 
Dev Process/Team StructureJul 1, 2005Aug 26, 2005 0
 
Dev Process/Team Structure first draftJul 1, 2005Jul 29, 2005 0Markus Gylling
 
Dev Process/Team Structure review and finalizationJul 29, 2005Aug 26, 2005 0Architecture Team, Management Team
 
Design Requirements Jul 1, 2005Aug 26, 2005 0Markus Gylling
 
Design Requirements first draftJul 1, 2005Jul 29, 2005 0Markus Gylling
 
Design Requirements review and finalizationJul 29, 2005Aug 26, 2005 0Architecture Team, Management Team
 
Onset Documentation complete and publishedAug 26, 2005Aug 27, 2005*0Markus Gylling, George Kerscher
 
Letters of UnderstandingJul 18, 2005Aug 26, 2005 25Management Team
 
Iteration 1Aug 29, 2005Oct 3, 2006 0
 
Management TeamOct 3, 2005Oct 4, 2005 0
 
decision on coding languageOct 3, 2005Oct 4, 2005*0Management Team
 
decision on licensingOct 3, 2005Oct 4, 2005*0
 
Inception TeamJul 1, 2005Dec 3, 2005 0
 
coding language selection documentationJul 1, 2005Sep 16, 2005 0Daniel Weck
 
f2f AmsterdamAug 30, 2005Aug 31, 2005 0
 
business modeling & requirementsAug 30, 2005Dec 2, 2005 0Inception Team
 
skeleton uml modelAug 30, 2005Dec 2, 2005 0Inception Team
 
Inception Team delivers and dissolvesDec 2, 2005Dec 3, 2005*0
 
Architecture TeamDec 5, 2005Mar 11, 2006 0
 
Complete UML representation of IT1 data model and APIDec 5, 2005Feb 28, 2006 0
"Object model level 1"; advancing of the UML model to meet a certain feature level (not complete; minimal but well defined; you can build a basic application from it)
Unit Test LibraryDec 5, 2005Feb 25, 2006 0
not necessarily complete; language-specific
Mods of Model following Impl team reviewMar 3, 2006Mar 10, 2006 0
 
Model, Unit tests and API documentation deliveredMar 10, 2006Mar 11, 2006*0
 
Implementation TeamFeb 28, 2006Jul 28, 2006 0
 
Final review of UML modelFeb 28, 2006Mar 3, 2006 0Implementation Team
Review has been ongoing since Architecture group onset
IT1 processor alpha 1Mar 10, 2006Jul 28, 2006 0Implementation Team
Starting point: 1. library of tests 
2. complete level 1 UML 3. coding standard
processor alpha 1 deliveredJul 27, 2006Jul 28, 2006*0
Deliverables:		
1. source code
2. unit test reports
3. binaries
4. implementation details not covered by UML or generated documentation
Application TeamDec 2, 2005Aug 4, 2006 0Application Team(s)
 
mockup UI and aux library modellingDec 2, 2005Mar 3, 2006 0Application Team(s)
 
UI and aux library developmentMar 13, 2006Jul 28, 2006 0Application Team(s)
 
UI and aux libs deliveredJul 27, 2006Jul 28, 2006*0
 
Release PackagingJul 28, 2006Aug 4, 2006 0Application Team(s)
 
Iteration 1 releaseAug 4, 2006Aug 5, 2006*0
 

Ganttproject (2.0-pre1)ganttproject.org
Jul 26, 2005 - 12:00:00 AM